Progress, with a chance of rain

February Construction Update 

We’ve had one of the mildest winters in recent memory, with no snow and only a few nights hitting freezing temperatures.

At the same time, we’ve had quite a few significant bursts of rain – 2 inches or more at a time. Such is the nature of winter construction in the Northwest.

The crews continue to work on footings and foundation walls at the north end of the site, including those for the Salal and Elan buildings.

Once the foundation walls are done for these buildings, the form work for the ceiling or “lid” of the garage will start. This will be the first peek for the public to get a sense of what we’re building as the main floors begin to take shape.