January 2015 Construction Update

The weather has certainly been mixed, but Grow Community construction continues apace. Crews have completed the majority of the excavation work and have now started forming and pouring footings and foundation walls for the garage for the Grove, our next neighborhood.

While progress may not always be apparent from street level, we are using a “UAV” – an Unmanned Aerial Vehicle, otherwise known as a “drone” – to keep a visual record of the construction process.

e3f6a04e-ba4a-4fe1-aa9c-4ade5fce5674
In the lower right corner of the accompanying aerial photo, you can see a series of white structures. This is actually a small part of the foundation and garage for a building in the Park, Grow’s third and final neighborhood.

This section of the last phase had to be built first in order to support the utilities and structures that will be uphill in the Grove. Construction sequencing can present challenges, but we always seem to figure out the right solutions!

The crews have also started in on the portion of the garage under the Salal building, and will march around to the northwest corner and then head south to form and pour the Elan townhome building next.

While the garage is being completed, the framing will start in earnest, so the two tasks – concrete foundations and framing – will be taking place at the same time.

We’ll be up out of the ground this Spring!