Spring has sprung at Grow Community, and our second and third neighborhoods are bursting forth.
First, at the Grove: Our last unit (D103) in the Tsuga is a very cool home, is now on the market, and move-in ready. With only five homes left in this building, the time to visit is now! Outside we’re doing some landscaping touchup and tree replacement – after one of our more memorable (read: cold and wet) winters, our plants are taking a bit more time to bud, but they’ll get there soon.
Next door at the Park: The Lilac Townhomes are in the finishing stage with prep for move-in now underway. All major work items are complete, with only cosmetic work left before the final clean. We’ve filed with the City of Bainbridge Island for occupancy, and we should see our first residents here by May!
The Sage remains on schedule for a summer completion. Elevator work, drywall and exterior siding installation are in process, while finish work on the inside (including cabinets) is expected to begin at the end of April. Landscaping throughout the Park will continue through summer.
Linking them all is the Community Center, where framing should be completed this month; roofing and windows will follow soon. You’ll see more activity around the center with the addition of new walks, planters and landscaping. We hope to host an event in this great new space (even during construction) to celebrate its importance as a new hub for our community – watch for an announcement in May!