As we build the Grow Community we will be chronicling our progress. This is the place for updates!

Grow Community Wins Built Green Project of the Year

This past Thursday (9/14), Grow Community received the Built Green Project of the Year at the annual Built Green Conference.

It was unexpected, and we are deeply honored to be given such an award considering the unbelievable work our peers have accomplished in 2017.

The Grow Team wishes to thank our investors, construction team, Built Green, our design teams, and the other builders that are pushing the envelope toward sustainability, and especially our Grow Community residents. Everyone has believed in possibility and found a way to make Grow a reality.

 

Sage advice — come to the Park and see the Lilacs. A Construction & Sales Update – August 2017

A warm summer has brought the Park neighborhood to life, resplendent with its first round of trees, grasses, pea patches and plantings.

Centerpiece is the new Community Center, where the planter beds have already been filled by enthusiastic neighbors looking forward to future harvests. The center’s solar canopy is now in place, with system installation set for October once the roofing is done. Inside the center final painting is underway, and the building should be completed by mid-September. Watch for upcoming events here as we start to bring the community together around the use of this great new facility.

Nearby the Sage building is wrapping up nicely with some new residents already moved in, and more new neighbors arriving over the next several months. New neighbors in the Lilac townhomes will follow.

Toward the south end of the project, grading and other construction activity will begin in September. We’ll be focusing on path work and prep for Grow’s final buildings, the Trillium and Meadow Homes. There’s no timetable yet for building construction, but we should have an update in the coming weeks.

The Grove neighborhood has settled in, with just four 2-bedroom homes still available.

The Lilac townhomes now have six homes ready and waiting — three 3-bedrooms (the last 3-bedroom homes left in all of Grow Community) and three 2-bedroom units as well.

All homes in the Sage condominiums will be completed by September, meaning more purchase opportunities are about to come online. Nine 2-bedroom units are available, including third-floor with spectacular views. This is your last chance to live in a single-level home in Grow Community! Contact the sales office today for a personal tour.

Nearing Full Flower. A Construction Update – July 2017

Summer is finally upon us, and it’s exciting to see our landscaping really taking off with the turn of another season. Grow Community is lush and green!

Our built environment too is nearing full flower. While we’ve wrapped up the Grove (with just a few units remaining), we are pushing toward completion of the Sage building in the new Park neighborhood.

The Sage will see its first residents moving in the latter half of July, with building completion in August. The exterior work is nearly done and all interior work is well into the last details. Landscaping comes right on the heels of exterior work and we hope to see all sides of The Park getting buttoned up.

The Lilac Townhomes have residents now moving in, and we are excited to see the community filling up in our final phase.

Our new neighborhood hub, the Community Center, is also taking shape with roofing nearly complete, siding soon, and interior work underway over the next week. Even the new planter beds are in place and nearly ready to let people get their plantings going! You’ll see the final site/landscaping work and solar canopy over the next several weeks.

Celebrate with us as we host a “soft opening” for the Community Center, with all-day events on Thursday, July 20. We’ll host a lunchtime BBQ for the construction team, have the building open for those who wish to swing by, and host an evening event celebrating the history of the Grow site and how it will be honored within the center. We truly look forward to sharing our history with the Bainbridge Community.

May 2017 Construction & Sales Update

That’s a wrap! With the singular “tall-skinny” unit in the Tsuga now complete, Grow Community transitions away from the Grove neighborhood and into our final phase. But if you’ve not seen that unit – a unique three-story layout, with a spacious outdoor deck on every level, a loft area for a home theater or den, and a private elevator to every level  –  stop in and see what make it so distinct.

Meanwhile, at the Park: The Lilac townhomes have earned occupancy certificates from the City of Bainbridge, with touch up work just wrapping up.  Our first owners will be in by the end of this month –   more amazing people joining Grow, whose homes all front the Park’s signature greenway.

The Sage condominium homes are on pace for completion from early July to early August. Interior work is underway, while exterior siding will be wrapped up by early June.

The Community Center will be taking shape through June with completion of the roof, windows, exterior siding and interior fixtures. We hope to host an event in the building in mid-June as a “soft opening” of the space, and transition control of the building to the homeowner association later this summer.

Landscaping and grounds items are also taking shape in the Park, and a little sun goes a long way. Watch the carpet of green roll its way south toward the Shepard Way end of the project, with construction of our final buildings there soon to follow.

With all these great units coming online, we’re still missing one thing: You. Six beautiful condos are now move-in ready in the Tsuga and Salal, and five townhomes including two spacious 3-bedroom units.

Not ready to buy? Experience Grow Community living in a 2- or 3-bedroom rental unit, now open in the Juniper.
Contact our sales office and see these outstanding units today, and join our community for healthy, happy living.

April 2017 Construction Update

Spring has sprung at Grow Community, and our second and third neighborhoods are bursting forth.

First, at the Grove: Our last unit (D103) in the Tsuga is a very cool home, is now on the market, and move-in ready. With only five homes left in this building, the time to visit is now! Outside we’re doing some landscaping touchup and tree replacement – after one of our more memorable (read: cold and wet) winters, our plants are taking a bit more time to bud, but they’ll get there soon.

Next door at the Park: The Lilac Townhomes are in the finishing stage with prep for move-in now underway. All major work items are complete, with only cosmetic work left before the final clean. We’ve filed with the City of Bainbridge Island for occupancy, and we should see our first residents here by May!

The Sage remains on schedule for a summer completion. Elevator work, drywall and exterior siding are in process, while finish work on the inside (including cabinets) is expected to begin at the end of April. Landscaping throughout the Park will continue through summer.

Linking them all is the Community Center, where framing should be completed this month; roofing and windows will follow soon. You’ll see more activity around the center with the addition of new walks, planters and landscaping. We hope to host an event in this great new space (even during construction) to celebrate its importance as a new hub for our community – watch for an announcement in May!

Seasons Turn – March 2017 Construction Update

The turn of seasons brings splendid new growth at Grow Community — Lilac townhomes are coming online, the first homes to be completed in our new Park neighborhood. Finish work is now underway inside the units, including counters and fixtures, while exterior details should be wrapped up over the next couple of weeks. Landscaping will follow, to the same lush standard of native greenery found throughout Grow’s first two neighborhoods.

Work continues on the Sage building, while the Community Center should begin to spring up from its concrete pad in the coming weeks.

Winter marches on, so too the final touches on Grow Community phase 2, the Grove

Finishing crews are now wrapping up the Tsuga’s “tall skinny” unit with its unique three-floor layout, while two recent sales elsewhere in the building mean we’ll be welcoming some more new residents to the community soon.

Meanwhile in the final phase of Grow, the Park:

The Lilac townhomes are coming along apace, with the completion date and move-ins beginning this spring. These fine 2 and 3-bedroom townhomes are now for sale.

Just across the grounds, work on the Sage is in full swing, with the roof nearing completion and finish crews going to town inside.

Permitting for the Trillium and Meadow Homes at the south end of the Park is still in process, but we are already prepping for work by removing excess dirt from the site. Progress on the Community Center (currently an expansive concrete slab) will resume once the framing crew is available.

And out in the Park grounds, site paths and concrete work continue as we begin knitting together “greater Grow”– the Village and Grove neighborhoods will soon be linked with the front of the Lilac by convenient pedestrian paths.

With the dark days of winter still upon us, can spring be far behind?

No! And that means you’ll soon see more landscaping work in both neighborhoods, as we do a final tidy-up of the Grove and work our way through the Park toward Shepard Way.

 

Come inside and look around — without leaving your chair

Want to experience Grow Community, but don’t have time to visit our model home?

Now you can take a virtual tour with a click of your mouse. Here’s a 360-degree video tour of our 2 bedroom model unit in the new Tsuga building in Grow phase 2, the Grove.

As the video rolls, use your mouse to scroll all around the room and even the grounds outside. See for yourself the spacious floor plans, fine craftsmanship and eco-friendly features — it’s almost like being here!

Note: To watch 360° videos, you need the latest version of the Chrome, Opera, Firefox or Internet Explorer browser. On mobile devices, use the latest version of the YouTube app.

There’s no place like Grow for the holidays

As the holidays approach, Grow Community puts a bow on another building and welcomes another season of lights across our beautiful neighborhoods.

In the Grove neighborhood, we’ve been approved for occupancy of the new 2-bedroom homes in the Tsuga building, and hope to see new residents joining us there in January. The “tall skinny” 3-floor home at the Tsuga is now nearing completion, and we’re checking off remaining punch-list items throughout the building.

Progress in the Park neighborhood continues with the Community Center‘s framing, roof and window work beginning next month and completion expected in spring.

 At the Lilac Townhomes, siding and interior work are well underway and the homes should be ready in late April. The Sage condominiums follow with roof and window work up next and anticipated completion in July.

That leaves only the Trillium and the Meadow Homes, which await building permits from the City – we look forward to starting these final structures so we can begin tidying up the last of our spaces and Grow Community moves toward final buildout.

We are grateful for everyone’s patience, as the big and small details come together and we move into our final year of construction.

Best and happy holidays to all!

Construction Update: As Thanksgiving Approaches…

With Thanksgiving almost here, we’re grateful for great new neighbors in the Grove and great progress throughout the Grow Community project.

All Woodland Homes are now complete and residents moved in, with only small punch-list items left to do. The Tsuga building is now partially occupied, with the remaining units ready for move-in this month. The ‘Tall and Skinny’ home will be wrapping up as well (ask about this very unique unit at our model home).

Landscaping in “The Knuckle” area west of the Woodland homes will begin this month, with connecting paths between the Village and Grove neighborhoods to be open by the end of the year.

In our third and final neighborhood, the Park, the Lilac and Sage are both progressing very well – both will have roofs on before the end of November.

Community Center framing will also be done before the calendar turns. Our goal is to get this building “dried in,” after which we’ll focus on community-supported decisions for the finish work.

Finally, the Trillium and Meadow Homes are both in varied stages of permitting. We hope to start these as soon as possible.